Disrepair Project

Saville House, E16

A legal disrepair refurbishment within an occupied property, supporting a vulnerable tenant throughout — restoring the home to a safe and habitable condition.

Client: London Borough of Newham Project value: £6,857.14

Key figures

  • £6,857.14

    Project value

  • Disrepair repairs

    Legal works

  • Multiple trades

    Coordinated

  • Safe & habitable

    Condition restored

  • NICEIC EICR

    Completed

  • Vulnerable tenant

    Supported

Project Overview

This project involved delivering a legal disrepair refurbishment within an occupied residential property. Works included internal building repairs, plastering, decorations, joinery repairs, and associated remedial works to restore the property to a safe and habitable condition.

A key challenge was working within an occupied property where the tenant had been identified as vulnerable and requiring additional support. Careful planning, clear communication and a patient approach were maintained throughout the works to ensure the tenant felt safe, informed and comfortable, while minimising disruption and successfully delivering the project.

Schedule a Call

Key Challenges

  • Delivering works within an occupied property.
  • Supporting a vulnerable tenant throughout the duration of the project.
  • Coordinating multiple trades, including NICEIC-certified electricians.
  • Managing additional defects through the CVI process.
  • Maintaining a safe, clean and organised working environment while minimising disruption.

Vulnerable Resident Support

Additional time and patience were given throughout. Noise, dust and disruption were minimised, works were planned around the resident's needs, and support was provided throughout the project to ensure the resident's comfort and well-being.

Scope of Works (SOW)

  • Complete legal disrepair repairs throughout the property
  • Carry out plastering and making good to affected walls and ceilings
  • Prepare and redecorate internal areas
  • Repair internal joinery and finishes
  • Complete associated remedial building works
  • Carry out a NICEIC Electrical Installation Condition Report (EICR)
  • Test all accessible electrical circuits and issue certification upon completion

Confirmation of Verbal Instruction (CVI)

  • Additional plastering and making good following opening-up works
  • Additional decoration to achieve a consistent finish
  • Minor remedial electrical works identified during testing
  • Additional repairs identified during the project and completed following client approval
  • NICEIC-certified EICR completed prior to handover

Our Disrepair Delivery Process

Resident Engagement & Pre-Start Liaison

Initial contact with the resident; pre-start meeting to explain works, programme and daily activities; support needs and access arrangements identified; single point of contact established.

Pre-Start Inspection & Condition Survey

Scope of works verified against site conditions; existing defects recorded with photos; additional repairs or hidden defects identified; programme and materials confirmed.

Health & Safety & Site Preparation

Site-specific RAMS completed; dynamic risk assessments carried out; resident belongings and areas protected; safe working zones and access established.

Project Delivery & Trade Coordination

All trades and works sequenced; multiple trades coordinated efficiently; additional works managed through the CVI process; communication maintained with client and resident.

Resident Communication & Progress Updates

Regular updates provided throughout works; progress reviewed with the resident at key stages; prompt responses to concerns or changes; additional support provided to vulnerable residents.

Quality Assurance & Photographic Evidence

Supervisory inspections at key stages; works photographed before, during and after; internal snagging and quality audits; works verified against the agreed specification.

Final Inspection, Walkthrough & Handover

Final quality inspection completed; resident walkthrough and feedback; client approval obtained; certificates (EICR) issued and project closed out.

Project Completion

  • All works completed to specification.
  • NICEIC EICR completed and certified.
  • Resident satisfied with works.
  • Property left clean and safe.
  • All documentation issued to client.

Schedule a Call

Services Delivered

  • Plastering & Decorations
  • Building Repairs
  • Joinery Repairs
  • Electrical Works (NICEIC)
  • Making Good & Remedials
  • Project Management
  • Disrepair Refurbishment

Looking Ahead

Green Birds Construction continues to invest in people, process and innovation to deliver exceptional construction and property services. We are ready to support councils, housing associations and property managers – delivering quality homes, safely and to the highest standard.

Schedule a Call